New building updates 4/23 |
|
|
4-23-2009
我們終於簽訂了裝修工程合同,工程工作從未停下來。師母和我剛到過施工現場,那裏將成為一個非常漂亮和實用的設施,讓我們能夠擴展我們的事工和榮耀神!教會辦公室和兒童部正包裝現有物資,預計在5月份首兩週進行搬遷。請繼續為新堂進展和我們的財務狀況祈禱。
招世超牧師
Progress
1. We have finally signed the contract on 4/21 (Tuesday). 2. The gas monitoring design has been approved by the City. HPM Systems based on the approved plan and prepared a proposal for the shelter-in-place gas monitoring system equipment. GC will provide installation of the system. 3. GC has started putting up all the electrical works and wall insulation since last Thursday. GC has scheduled the last round of frame and electrical inspection on 4/23 (Thursday). If the works get passed the inspection, GC will put up the drywalls right after and all the walls will be finished by next week. 4. GC has revised the schedule accounting for the 6 days delay and now the new completion date is June 4th. 5. Please continue to pray for the progress and our financial situation as we need to start paying the GC for the work after signing the contract.
|
4-23-2009