New building updates 4/2 Print E-mail

4-2-2009

最近如果你有機會瀏覽我們的網站,看看兩天前有關我們的新堂的照片,你會發現內部框架已經差不多完成。在上星期日的祈禱會中,我跟參加的弟兄姊妹們分享了我到現場看到了框架的感受,神的恩典是超乎我們想象的。7年前,當我們還在裝修我們現有的設施時,我在講台所在的空地上來回踄步,想像在還末建成的Golden Hall內對着滿座的會眾講道的情景。現在,我們每個主日有3堂崇拜,在兩個月後將要搬進入我們的新堂。新的禮拜堂會有現時Golden Hall兩倍的容量。這將會是我們的挑戰,要座滿這個可以席位容納超過400人的地方。神啊,我們願意伸出我們雙手拖引更多的人進入你的王國!

招世超牧師



Progress

1. Demolition work completed last Friday (3/27). Scheduled inspection (4/1).
2. Ordered major AV equipment on 3/31 before the tax increase by 1% on April 1st. Proposal ready by Friday for review.
3. AT&T completed installation 2 phone lines on 4/1 for the temporary fire monitoring system.
4. Change order to take off the glass wall and a door b/w sanctuary and conference room done on 4/1. To solve acoustic problem during Sunday worships and reduce costs.
5. Finalized flooring selection on 4/1.
6. Continue to work on roof leaking issues. Further discussion when the contract is finalized.
7. Have not received finalized contract. Continue to follow up with GC.
8. Structural work has been going smoothly but not 100% on schedule due to unexpected change orders.
9. Cannot move in prior to the substantial completion (5/28).  Please keep praying for the progress and hope that GC will catch up some delays in the next few weeks of work.

4-6-2009


View Slide Show

4-1-2009


View Slide Show

 