Progress

1. 3/10 Demolition Permit obtained
2. 3/17 Demolition work started (to be completed by 3/23)
3. 3/17 Submitted Address change request to City (to correct a mistake)
4. 3/17 Arranged site walk-thru with City Inspector and okay.
5. General Contractor (GC) to coordinate with Testing Company to X-Ray shear wall
6. GC to work on contract and verify base price
7. 3/20 Review contract
8. GC and church committee to work on issues on fire monitoring system, sinks and blinds
9. Sent out requests to 4 cabling subcontractors for quotes
10. (next week) Architect to send us the finishes and samples for our review and approval